Henry County has various road projects in progress, paid for by SPLOST and Georgia DOT. Here are the latest updates on Henry County road projects as of August 2024.
The county’s transportation advisory group meets quarterly. Henry County staff shared these updates with the committee on Monday, July 29.
Henry County Road Projects August 2024
Major Road Projects & Road Widening Projects
SPLOST V Projects
- McDonough Parkway at State Route 20 – Construction Notice to Proceed issued on May 1, 2024.
Editor’s note: this project will improve McDonough Parkway near Patrick Rentals at its connection with Georgia 20. The state is presently widening Georgia 20 to four lanes. Their project includes a new roundabout at McDonough Parkway. In addition, the state’s contractor will tie Georgia 20 into Henry Parkway Connector. This will open the new road when the SR 20 widening is complete. - Flippen Road extension, between Jonesboro Road at North Mt. Carmel Road, Dutchtown Schools and Stratford Circle – Construction bid awarded to Southeastern Site Development in April 2024.
- Fairview Road widening, between Home Depot and Hearn Road – Right of way acquisition starting soon.
Explore
Henry County voters will consider approving SPLOST VI this November. Check out the project list!
Transportation SPLOST Projects
- State Route 81 widening, phase I, between Postmaster Drive and Bethany Road – Right of way acquisition in progress. The tentative construction bid date is in May 2025.
- Bill Gardner Parkway widening, between I-75 and state route 155 – Right of way acquisition in progress.
- Jonesboro Road widening, between Mill Road and North Mt. Carmel Road – Right of way acquisition in progress.
- Mill Road widening, between Jonesboro Road and Peachtree Peddler’s Flea Market – Right of way acquisition in progress.
- McDonough Parkway, north segment, between state route 42 and state route 155 – Construction bid awarded to Southeastern Site Development in April 2024. Notice to Proceed issued on July 15; clearing in-progress.
- Rock Quarry Road widening, between SR 138 and Eagles Landing Parkway – Construction bid date planned for January 2025 (updated date on August 19).
- Fairview Road widening, between Hearn Road and SR 155 – Right of way acquisition to begin in August 2024.
Other Projects
- State Route 81 widening, phase II, between Bethany Road and Keys Ferry Road – RFP for design firm / engineering work in progress.
- Mill Road widening, phase II, between Peachtree Peddler’s Flea Market and state route 81 – design contract awarded to Transystems on June 25. Design Notice to Proceed issued on July 22.
Georgia DOT Projects
Projects Under Construction Now or Coming Soon
- State Route 20 / 81 widening, between I-75 and Phillips Drive – Construction began in March 2023; estimated completion date is in May 2025.
- State Route 42 widening, between I-675 and SR 138 – Construction began in October 2023; estimated completion date is in August 2027.
- State Route 42 widening, between Bill Gardner Parkway and Peeksville Road – Construction began in November 2022; estimated completion date is in October 2024.
- Western Parallel Connector, a new four-lane road between Hudson Bridge, Jodeco and Jonesboro Roads – Construction award approved in July 2024; estimated completion date is in November 2026.
- SR 81 at New Morn Drive – Construction is out for bid; bids due on August 16, 2024. The project will build a new roundabout.
- State Route 20 resurfacing, between I-75 and Lower Woolsey Road – estimated construction bid date is in September 2024.
- SR 20 at McGarity Road & Lawrenceville Street – project will construct dual roundabouts at the two intersection; estimated construction bid date is in November 2024.
Pre-Construction Projects
- State Route 42 widening, between SR 138 and Downtown McDonough – the project is in design. Right of way acquisition is scheduled for 2027–28 and construction is scheduled to start in 2030.
- State Route 155 widening, between I-75 and SR 42 – the project is in design. The project has recently started right of way acquisition and construction is scheduled to start in late 2027.
- SR 155 widening, between I-75 and Hampton-Locust Grove Road – concept development is in progress. Concept report submission is expected in the 3rd quarter of 2025. Right of way funding is in FY 2028, and construction is budgeted in 2030.
- SR 42 Bridge Replacement over Norfolk Southern Railroad, near Harris Drive – construction budgeted in FY 2026.
- I-75 Commercial Vehicle Lanes, between I-475 / Macon and McDonough – construction estimated to start in 2026 and conclude by 2031.
- I-75 Express Lanes Expansion, between I-675 and SR 155 – project announced in July 2024; engineering work next.
- New I-75 Exit at Bethlehem Road – design plans presented in April 2023. Right of way acquisition scheduled to start in 2025 and construction is estimated to start in 2026.
MHF News is providing this article for free as part of our efforts to share updates with the Henry County community. Please directly support our work by subscribing today — get 3 months for $25!
Intersection Improvements
- Bridges Road at Willow Lane – Complete.
- Racetrack Road at Iris Lake Road – Complete.
- Airline Road at McGarity Road – Right of way acquisition in progress.
Dirt Road Paving Projects
- Dutchtown Road – Right of way acquisition in progress.
- Knight Drive – Construction bids in progress; bids due on August 28.
- Burg Road – Right of way acquisition is 90% complete as of June 14, 2024.
Other Projects
- LMIG 2023 & 2024 Road Resurfacing – Construction bid awarded to MHB Paving. Notice to Proceed issued on April 21, 2024.
- 2024 Road Resurfacing Contract 2 – Construction contract awarded to Blount Construction Company in June 2024.
- Fairview Road sidewalks, between Anvil Block Road and the DeKalb County line – Construction bids in progress; bids due on August 28.
Featured image shows Road Work Ahead sign on a divided highway. Georgia DOT photo.
Be the first to comment